Critical Path of the As Built Schedule
In the Open Standard
US
Uri ShacharMember for 23 years 5 months
- Created
- 13
- 5
0
My feeling is that there is no such thing. activities that happened in the past have actual values, and therefore can not be critical. This is why comparing the as built with the as planned schedule is not legitimate. Can anybody comment? Is there any literature about the above?
13 replies
Oldest first- 0RWRonald Winter ·This is a common misunderstanding. Please see my page http://www.ronwinterconsulting.com/apab.htm for a complete discussion of this issue. I will be presenting a paper on this subject at the AACEi Users Convention on June 13-16, 2004 in Washington. There is nothing that the mind of man cannot do,
- 0USUri Shachar ·Roland, thank you for your answer. For most contracts, the contractor is entitles to an EOT not for actual delays to the date for completion, but for any PROSPECTIVE delays to the anticipated date for completion as impacted by the delay when occured, regardless of whether there was an actual delay or not.
My point is that the actual CP as reflected in the "as built" programme would mean nothing under such circumstances. - 0SSStevan Sarapa ·Ronald,
my boss wants me to determine critical path on the as-built subcontractor schedule of 1900 activities. Actually this should be done in order to find out all delays that had impact on completion date. After that each (critical) delay will be analyzed separately and divided into 3 categories (inexcusable , excusable and compensable). Schedule is done in Microsoft Project so I do not think I ll be able to follow suggestion from your web page "How to manually determine the As-Built Critical Path". I am just wondering is it possible to create a new schedule with early start and finish dates same as from actual schedule and using logic (links) that I believes were realistic. If the link does not drive activity then additional activity will be added i.e. "Start delay" so that early start really matches actual start date.
Does this make sense?
Best Regards,
Stevan Sarapa - 0COCharleston-Joseph Orbe ·Hi,
Critical Path of As-built Schedule does not make sense because the activities were finish. How on earth completed activties becomes critical - "kalas or finish". There is no point in banging your head in analysing critical path of completed activities.
On the other hand, for forensic analysis in resolving claims it do make sense.
Cheers
- 0SDSe de Leon ·Hi Uri,
There was a long debate already about the topic in this same category i.e. Contracts, Claims... It is entitled Critical Path History and As-built Critical Path. This topic could be one of the most debated topics here in PP.
Me too I’m of the opinion that as-built critical path strictly speaking, is not the correct term. For me, Critical Path History is more appropriate.
Cheers,
Se - 0RIRaja Izat Raja Ibrahim ·Hi,
Lately a lot of new definition, I couldn’t understand where it come from.... like As built schedule, lean schedule or what ever..... is this related how to make words looks very technical. Sorry, to say maybe i far behind from the hi-tech world. To me there is no as-built schedule...only i know is Preliminary(draft), Rev.1, Rev.2 etc.
About critical Path, it being analyse to achieve smooth working access to meet target date without any interface because there is no float. - 0USUri Shachar ·Phil,
Welcome to the forum. To me, there are two issues here:
1. Is there an As Built Critical Path? (see previous discussions). Can activities with actual start and finish dates be critical (look in your planning software - is this possible?)
2. Is the As Built Critical Path (assuming there is one) relevant to the Analysis of Delays (for most forms of standards Contract the delay should affect critical path AT THE TIME OF THE DELAY, not when the works are completed). - 0PBPhil Butler ·Uri
Obviously activities that have finished have no float and therefore no critical path can be identified. However, on most projects I have worked on I have been asked to look at the "as-built critical path". Whilst this does not exist using the longest path gives a good indication of which activites were driving the finish of the project.
I agree that most contracts these days call for delays to be analysed using the programme at the time of the delay, however you still end up with global claims at the end of the project that require a certain amount of historical planning.
In an ideal world all delays would be analysed as they occur, however this is not always possible on projects due to the pressures of the work on site, such is life!
Regards - 0SSStevan Sarapa ·Dear All,
I would like to remind that it is possible to establish critical path on as-built schedule (actual finish dates should be replaced with expected finish constraint)as it was explained on Ronalds site (see his link below). But, i m not sure if my proposal is ok.
Thanks,
Stevan Sarapa - 0COCharleston-Joseph Orbe ·Hi Phil,
I addition to what was said, some of the delays can not be analyze as they occured. This is true in situation where the event that cause the delay is continuing at the time of assessment of delay. In this case it will be premature to analyze the delay.
Cheers - 0USUri Shachar ·Guys,
I think the UK SCL Delay & Disruption Protocol addresses most of the issues raised here.
GLOBAL CLAIMS are very difficult to substantiate since there is no ’casue and effect’. Try to avoid if possible.
Continious delays should be assessed at key milestones during the time when the delay is active. Obviously, the more ’snap-shots’ one takes the more accurate the analysis.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?