WBS
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 1
- 1
0
Hello
I create a WBS for a project. It is composed from three (03) levels. To up from the lowest level to an up level I need weighting
I explaine what I mean:
Exp
Level 02 Piping
Level 03 : Pipe cutting
Welding
Fiting Installation
Hydrotest
Reinstatement
To weight those activities will I use the price of each activities divided by the overal price of piping (L2) or have I to count the manhoures of each activity and I divided by the overall Manhoures of piping activity.
Thanks for your help.
I create a WBS for a project. It is composed from three (03) levels. To up from the lowest level to an up level I need weighting
I explaine what I mean:
Exp
Level 02 Piping
Level 03 : Pipe cutting
Welding
Fiting Installation
Hydrotest
Reinstatement
To weight those activities will I use the price of each activities divided by the overal price of piping (L2) or have I to count the manhoures of each activity and I divided by the overall Manhoures of piping activity.
Thanks for your help.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?