WBS

Forum GuestMember for 17 years 8 months
Created
1
1
0
Hello
I create a WBS for a project. It is composed from three (03) levels. To up from the lowest level to an up level I need weighting
I explaine what I mean:
Exp
Level 02 Piping
Level 03 : Pipe cutting
Welding
Fiting Installation
Hydrotest
Reinstatement
To weight those activities will I use the price of each activities divided by the overal price of piping (L2) or have I to count the manhoures of each activity and I divided by the overall Manhoures of piping activity.
Thanks for your help.

1 reply

Oldest first
  1. 0
    Ernesto Montales ·
    the steps you mentioned is a good way, typical way to give weight the major phase of a project. Its either by money or manhours. The only problem with this method is that it is static in nature. To correct this we must schedule the phase of each item using soft and hard constraint in any project management software. In this manner we are able to monitor critical activities which very vital for claims in the future,

    Regards

    E. Montales
    Datem Construction

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?