Vishwas BindiganavaleMember for 22 years 5 months
- Created
- 5
- 4
0
Hi All,
The recent embargo on cement & steel in the Middle East has crippled concrteing activities and in-turn the project schedule. For example, our project slabs are ready for concrete pour well on time but we are forced to pour concrete only when the RMC supplier is able to procure cement. As slabs lie in the critical path, the entire programme shows delay on updation.
Contractually speaking, the main contractor has no right to claim for an extension of time as we ourselves are not procuring the cement stocks. Moreover, the contract has approved the said RMC supplier.
I would like to know if there is anyway we can claim an extension of time? I had written to the Consultant/Client regarding this claiming EOT with regards to Clauses 12.2/12.3(Adverse Conditions) and 44.1.e(Special Circumstances). The Consultant turned it down stating that these were not the right clauses for EOT claim. He also stated that local government did not recognise the shortage and hence the claim was baseless. Moreover, there is no "Force Majore" clause in the contract.
Can u guys give me a breather?? Its suffocating to continue like this.
The recent embargo on cement & steel in the Middle East has crippled concrteing activities and in-turn the project schedule. For example, our project slabs are ready for concrete pour well on time but we are forced to pour concrete only when the RMC supplier is able to procure cement. As slabs lie in the critical path, the entire programme shows delay on updation.
Contractually speaking, the main contractor has no right to claim for an extension of time as we ourselves are not procuring the cement stocks. Moreover, the contract has approved the said RMC supplier.
I would like to know if there is anyway we can claim an extension of time? I had written to the Consultant/Client regarding this claiming EOT with regards to Clauses 12.2/12.3(Adverse Conditions) and 44.1.e(Special Circumstances). The Consultant turned it down stating that these were not the right clauses for EOT claim. He also stated that local government did not recognise the shortage and hence the claim was baseless. Moreover, there is no "Force Majore" clause in the contract.
Can u guys give me a breather?? Its suffocating to continue like this.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?