Unsubstantiated Claim
In the Open Standard
Rajeev KumarMember for 23 years 5 months
- Created
- 5
- 3
0
Hi friends,
I have a situation here. Project Duration from Aug’03 to Feb’05. Clause 14 program submitted and appproved in Nov’03. The clause 14 program does not have much details, and has very long activities some spanning to 6-7 months.
Now the contractor has submitted a claim regarding a delay in issue of some kind of No objection Certificate, supported with letters and documents.The delay seems to be genuine and also a program showing the delay he encountered because of the late issue of the NOC. He just picks some related activity from the Clause 14 program and puts the new issue date on the bar and there goes the subsequent activity( an activity if duration 180 days), outside the contractual completion date.
my questions are:
1)How can I counter their arguement? Can I ask them to show the critical path within that long activity?
2)Will I Have to look for some other reasons because the Clause 14 Program was already been approved?
3) Or should I tell them, delays will be assessed on an actual basis and not necessarily as blindly shown on the Program?
Any help will be appreciated. Thanks for listening too.
Regards
I have a situation here. Project Duration from Aug’03 to Feb’05. Clause 14 program submitted and appproved in Nov’03. The clause 14 program does not have much details, and has very long activities some spanning to 6-7 months.
Now the contractor has submitted a claim regarding a delay in issue of some kind of No objection Certificate, supported with letters and documents.The delay seems to be genuine and also a program showing the delay he encountered because of the late issue of the NOC. He just picks some related activity from the Clause 14 program and puts the new issue date on the bar and there goes the subsequent activity( an activity if duration 180 days), outside the contractual completion date.
my questions are:
1)How can I counter their arguement? Can I ask them to show the critical path within that long activity?
2)Will I Have to look for some other reasons because the Clause 14 Program was already been approved?
3) Or should I tell them, delays will be assessed on an actual basis and not necessarily as blindly shown on the Program?
Any help will be appreciated. Thanks for listening too.
Regards
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?