Skip to content

EOT substantiation

Vishwas BindiganavaleMember for 22 years 5 months
Created
7
1
0
Hi All,

The following has been giving sleepless nights for a long time. The situation is like this -
1. UB Slab Target Completion - May 26, 2004
2. UB Slab Actual Completion - June 10, 2004
3. UB Columns Taget Completion - June 6, 2004
4. UB Columns Actual Completion - June 15, 2004
5. GF Slab Target Completion - June 13, 2004

*(Now is the hitch)

6. Consultant instruction to reduce slab levels in periphery - June 20, 2004.
7. GF Slab Actual Start - July 4, 2004 (after redesigning of slab)

At the time of issue of revised slab levels the project was showing a delay of 17 days. A claim was raised for EOT but, turned down by the consultant as the they claimed that the instruction was not in the way of the natural progress of works as the delay was already 17 days.

How do I claim for EOT now? ANd, what would be the substantiated claim?

Vishwas

7 replies

Oldest first
  1. 0
    Stuart Ness ·
    Hi Vishwas,

    What was the original Target Start date for the GF Slab and what is now the revised Target Completion date for the GF Slab? If possible, can you also say what the Actual Completion date was for the GF Slab?
    Is there any float in the GF Slab activity, and if so, how much?

    In addition, is the existing 17 day delay the responsiblity of the Consultant/Owner due to his earlier actions (or non-actions)?

    Cheers,
    Stuart
    www.rosmartin.com
  2. 0
    Vishwas Bindiganavale ·
    Hi Stuart,

    GF Slab comes on the Critical Path &, hence, no float. Also, the existing 17 days delay was not because of the consultant.

    GF Slab Target Start = June 02, 2004
    GF Slab Target Finish = June 13, 2004
    GF Slab Actual Start = July 04, 2004
    GF Slab revised target finish = July 18, 2004 (or actual finish)

    Hope this helps.

    Vishwas
  3. 0
    Stuart Ness ·
    Vishwas,
    Thanx for your clarification, and I am sorry for these supplementary questions: still not got my brain in top gear! ;-)

    At the time of receiving the instruction from the Consultant (20 June) you had completed the UB Slab and Columns. According to your original schedule, you should have started on the GF Slab on 2 June, this being 4 days before the end of the preceeding activity for the colums. You should therefore have been expected to start on the GF Slab 4 days before the actual end of the UB Columns, i.e. on (15-4) 11 June.
    Did you commence work on the original GF Slab (before the design was altered by the Consultant)? If so, when did you start?
    If not, why not (such as you anticipated a design change coming along anyway, perhaps??)

    Further to your earlier reply, can I assume that the Contractor was responsible for the earlier 17 day delay?

    Cheers,
    Stuart
    www.rosmartin.com
  4. 0
    Vishwas Bindiganavale ·
    Stuart,

    Most of your assumptions are right. We were supposed to have started the GF slab 4 days before the actual completion of the UB columns. (i.e. June 11, 2004). Not only did we anticipate the design change, but, we were also given verbal instructions of the design change. Unfortunately, the site team was not alert enough to confirm the verbal instruction on paper. And, yes, the 17 days delay at the time of formal instruction for design change was because of the contractor.
    I really appreciate your line of thinking. Now, I can imagine what your next move would be. But, I prefer waiting for your inputs, anyway.
    Also, please understand that the original duration for columns are 9 days and for slab it is as follows -
    UB Slab - 13 days; GF Slab - 10 days.
    If you still feel the details provided so far are not satisfactory, please feel free to mail me at vishbin_bhc@hotmail.com.

    Vishwas
  5. 0
    Stuart Ness ·
    Vishwas,
    Thanx for the additional input.
    As you have probably already worked out, your EOT entitlement is measured by the planned and actual finish dates of your GF Slab.
    The scheduled completion of the GF Slab was 13 June, but you actually completed 34 calendar days (30 work days) later on 18 July. The reasons for this delay are threefold:
     Enforced delayed start to the GF slab;
     More time required to cast and complete GF Slab.

    The enforced delayed start to the GF slab was itself caused by three further reasons:
     Expectation of instruction to change;
     Late issue of instruction to change; and
     Existing 17-day delay to the Works.

    There is a 30 working day delay (13 June to 18 July) in the finish to the GF Slab (assuming a 6 day work week). The instruction to change was issued in the middle of this period (20 June) and it no doubt required a re-engineering of the design for the GF Slab. In addition any pre-production of rebar and formwork for the original slab design was also probably abortive. I have no doubt that you can argue that the time from issue of the formal instruction on 20 June until start of the construction of the slab on 4 July was a fair and reasonable time frame for the re-engineering work and for a re-work to the formwork and rebar. Therefore, it was not unreasonable for you to start the GF Slab on 4 July.

    If there had been no instruction to change the GF Slab, the Contractor would have been expected to commence work to the GF slab on 12 June. This is based on the fact that under the Schedule, work to the GF slab was to start 3 days before the completion of the UB columns. Since the columns were completed on 15 June, the GF slab should have started on 12 June. However, the Contractor anticipated an instruction related to the GF slab, which was duly issued on 20 June, and arising out of this delayed instruction, the Contractor could not start until 4 July.
    Because of the Consultant’s instruction, the Contractor was prevented from making a meaningful start to the GF slab until 4 July, which represents a delay of 28 days measured against the original planned start date of 2 June.

    Under the original schedule, the GF slab should have been completed on 13 June, whereas the actual construction of the GF slab was completed on 18 July. This represents a further delay during construction of another 2 days. I would argue that you are entitled to the extra 2 days for reduced productivity due to the out of sequence nature of the late instruction.

    The total amount of the delays through to the end of construction of the GF slab is therefore (28+2) 30 days.

    However, the Contractor is responsible for 17 days of this delay, so the Contractor’s entitlement to additional time becomes (30-17) 13 work days. If this remains on the CP, the Contractor should be entitled to an EOT and his time-related costs for this 13 day period.

    In addition, the Contractor should also be entitled to disruption costs related to the rework of the engineering and any abortive material costs arising out of the late instruction.

    The Consultant’s argument, however, is that the Contractor was already late, so the fact that he issued an instruction on 20 June was not relevant. Mmmm…not quite true!

    As noted above, the Contractor expected to start the GF Slab on 12 June; this is based on the premise that under the original schedule, he was expected to start the GF Slab 3 days before the completion of the UB Columns. Since the columns were actually completed on 15 June, then the Contractor would have expected to start the GF Slab 3 days earlier, on 12 June. Therefore, the issue of an instruction by the Consultant was very much a delaying matter and it caused undue disruption to the Contractor, since it was issued beyond the date when the Contractor reasonably anticipated starting the GF Slab. However, in view of the expectation of a change, the Contractor opted to wait until he received formal instruction.

    In truth, what the Contractor did was that he mitigated the effect of the forthcoming instruction. By waiting until he received the formal instruction, the Contractor did not incur the additional costs of constructing the GF Slab, which otherwise would have had to be broken out and the total costs thereof would have been charged to the Owner.

    The Consultant’s instruction was untimely and he is therefore wrong in denying the Contractor the additional EOT, time-related costs and disruption costs.
    In addition, I note some acceleration of the UB Slab and Columns, so I would also question as to whether or not the delay attributed to the Contractor really was as much as 17 days.

    If this is still unclear, Vishwas, I can produce a more coherent narrative and causal connection, but I hope that this version is at least understandable.
    Please let me know if you need to have any part of it clarified, and of course, if you think that I have got any of it wrong, please let me know.

    Cheers,
    Stuart
    www.rosmartin.com
  6. 0
    Vishwas Bindiganavale ·
    Hi Stuart,

    Thanx for the inputs. Remind me to buy you a drink in case we ever meet in the future!!

    Btw, I have raised a claim to the consultant, and it is more or less similar to the input you have provided. I’ll keep you updated when I get a reply back from them (that should be by the 1st week of August 2004).

    Vishwas
  7. 0
    Stuart Ness ·
    Hi Vishwas,
    Glad I could help ;-)
    Please keep me posted on developments (love to see the counter-argument of the other side...!)

    Cheers,
    Stuart
    P.S. Mine’s a large one ! (the drink I mean!)

    www.rosmartin.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?