Critical Path of Contract Programme
In the Open Standard
Uri ShacharMember for 23 years 5 months
- Created
- 1
- 1
0
Guys,
I have a situation in which my client, the Contractor resource linked the Contract programme so that nearly all activities are critical. The Client does not accept these links, and his position is that only the sequence links are critical. The Contractor says that he resource linked the programme because this is how he costed his project.
I think the contractor is entitled to link however he wants (providing that the links are reasonable).
What do you think?
I have a situation in which my client, the Contractor resource linked the Contract programme so that nearly all activities are critical. The Client does not accept these links, and his position is that only the sequence links are critical. The Contractor says that he resource linked the programme because this is how he costed his project.
I think the contractor is entitled to link however he wants (providing that the links are reasonable).
What do you think?
1 reply
Oldest firstLog in or join to reply