Skip to content

CONCURRENT DELAY

Sooraj G OthayothMember for 21 years 9 months
Created
3
2
0
Hi,
I have a problem in which there is a contractor delay and employer delay for a particular activity. Both these have independent critical path delays (negative total float). TF of employer delay is less than that of contractor though both are negative. (say -25 for employer activity and -50 for contractor activity).
Can the employer ask for EOT and apportionment from employer in this case.
sooraj

3 replies

Oldest first
  1. 0
    Roger Gibson ·
    Sooraj,

    According to most forms of contract, the Contractor is entitled to an EOT for the Employer delay, regardless of any concurrent delay caused by himself.

    However, it is not the same for damages. The Contractor should identify & isolate the costs associated with the Employer caused delay. In practice, this is not so simple as it sounds.

    Roger Gibson
  2. 0
    Sooraj G Othayoth ·
    thks Roger,
    In my case the contract remains silent on concurrent delays. What happens under such situations
    sooraj
  3. 0
    Roger Gibson ·
    Sooraj,

    If the contract is silent on concurrent delays, then don’t mention it. Just make a submission for an EOT based on the Employer caused delay.


    Roger

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?