Hi Guys
i just wanna ask three simple questions...
First
who has the right to use the total float...Contractor or Consultant or owner???
Second
in my case i’m Owner Rep.& Main Contractor, the Sub-contractor used all the float and fall behinde schedule, where the schedule becomes fully backloaded (Construction)
the Sub-Contractor did not follow the targeted sequence of construction,(program prepared by owner)
meanwhile he always update the program that he does not want to follow (our program)
and now he is claiming for E.O.T on their actual sequence of construction which have nothing to do with our sequences presented in our program.
note..we r responsible for some delays regarding the issuance of drawings and some changes as well.
so, what do u think of this case since it is kind of complicated...but your contributions will be very helpful
Third
is the program approved by defualt if the Sub-contractor updated it several times???????????
note that the contract wording ia always talking about approved program
thanx in advance
i just wanna ask three simple questions...
First
who has the right to use the total float...Contractor or Consultant or owner???
Second
in my case i’m Owner Rep.& Main Contractor, the Sub-contractor used all the float and fall behinde schedule, where the schedule becomes fully backloaded (Construction)
the Sub-Contractor did not follow the targeted sequence of construction,(program prepared by owner)
meanwhile he always update the program that he does not want to follow (our program)
and now he is claiming for E.O.T on their actual sequence of construction which have nothing to do with our sequences presented in our program.
note..we r responsible for some delays regarding the issuance of drawings and some changes as well.
so, what do u think of this case since it is kind of complicated...but your contributions will be very helpful
Third
is the program approved by defualt if the Sub-contractor updated it several times???????????
note that the contract wording ia always talking about approved program
thanx in advance
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?