Skip to content

Delay Analysis Methods

David BarryMember for 23 years 9 months
Created
10
5
0
What is the most effective / reliable delay analysis methodology?

10 replies

Oldest first
  1. 0
    Gary France ·
    David,

    Very good question. The words cat and pigeons come to mind.

    I predict this might become a hotly debated thread.

    Prepare for many answers.

    Gary France
  2. 0
    Roger Gibson ·
    David,

    Let me be the first to put forward ’Windows’ methodology as the most reliable to produce the ABCP. As you are aware, this is a series of time-slices based on progress updates at say monthly intervals in accordance with progress reporting during the project. With ’windows’ analysis the criticality as determined at the time-slice is traced back to the start of the ’window’ as activities completed during the window will not show up on the time-slice as being critical.

    My personal view is that as the criticality of an activity at the ’window’ update, or time slice, is based on its path (activity durations & logic) to completion of the project, then the remaining network must undergo a ’reliability’ exercise to verify activity logic and durations and also that it represents the contractors intent as at the time of the update. This should be done at every ’windows’ update and the Analyst/Expert should give his reasoning for any changes resulting from the reliability exercises.
  3. 0
    Vladimir Liberzon ·
    Spider Project keeps project archives. At any moment you can open any previous project version and compare any two of them. At the line of balance presentation you can launch a movie that shows project performance (planned and actual).
  4. 0
    Gary France ·
    David,

    I have just written a reply to a posting in the As Built Critical History thread that is equally as relevant to this thread. This is partly about the choice of delay analysis methods.

    I won’t repeat it all here, but it sets out my some of my views about how to go about choosing the most appropriate method.


    Gary France
  5. 0
    Philip Jonker ·
    Agreed Gary, By the way Vladimir, P3 and even the old open plan DOS V4 had history features, spider is nothing new.
  6. 0
    Philip Jonker ·
    What I am talking about is 15 years old at least Vladimir, nothing new

    Regards
  7. 0
    Vladimir Liberzon ·
    Philip,
    I have thought that I know P3 and Open Plan capabilities.
    If you will explain me how to compare current project schedule with the schedule that existed one week ago, one month ago, two months ago, one year ago, etc. I will be grateful. Besides I want to be able to open project schedule as existed on February 1st or any other date in the project history. It does not matter if you will explain P3 or Open Plan features.
    Thank you in advance,
    Vladimir
  8. 0
    Vladimir Liberzon ·
    Philip,
    I want just to remind you that I am waiting for your answer in case you missed my posting.
    Best Regards,
    Vladimir
  9. 0
    Philip Jonker ·
    Hi Vladimir,

    In P3 inder ’Tools’ you have a function ’Store period performance’, which you can use to store period performance, after every update. In OP v4 you had a facility, called ’history’ with which you could do the same. In fact as I recall, you could use the history files, to retain the correct percentages after updates, for s-curves. Another simple way of capturing history, is to export the fields you would require to database files.

    Regards,

    Philip
  10. 0
    Vladimir Liberzon ·
    Does it mean that storing period performance I can open project schedule as it was at any date in the past and compare this schedule with the current or any former schedules with each other? We discussed Critical History and delay analysis and I mentioned storing project history for analyzing which activities were critical in the past, what changes were made at what time, etc. I did not understand from your post if these functions are supported.
    You were right about nothing new - Spider Project keeps project archives since version published in 1993.
    Thank you,
    Vladimir

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?