Nominated Subcontractors
In the Open Standard
Jihad DanielMember for 21 years 5 months
- Created
- 4
- 4
0
If the Owner nominated Companies for Electrical and Mechanical works inside a Building and instruct the Main Contractor to enter into subcontracting agreements with them. If the subcontractors delayed in performing their works (late delivery of materials, late mobilization of their resources, etc.),the Contractor would be responsible for the delays incurred by them? If project could not be handed over on time because of these S/Cs’ delays and if Owner decided to apply liquidated damages,how could the Main Contractor transfer the amount of liquidated damages if the ones of the S/C agreements are less than the one of his Contract with the Engineer/Employer?
Thanks & Regards,
J. Daniel
Thanks & Regards,
J. Daniel
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?