Secured Advance
In the Open Standard
Shahzad MunawarMember for 23 years 3 months
- Created
- 3
- 4
0
In mostly Contracts, the Contractor claims secured advance @ 75 % of total material value at Site in his Interim Invoices which is paid and then deducted from next invoices but the Contractor bears additional tax in this respect .
Example is as under:
Material at Site : $ 500,000
Previous Bill : $ 200,000
Material at Site This Bill: : $ 300,000
Less withholding tax @ 1 % : $ 3,000
Net payable Amount : $ 297,000
Does the Contractor bear the losses of 1% of additional tax from his each invoice when he claims Secured Advance or get benefit of 75% advance each month .
Example is as under:
Material at Site : $ 500,000
Previous Bill : $ 200,000
Material at Site This Bill: : $ 300,000
Less withholding tax @ 1 % : $ 3,000
Net payable Amount : $ 297,000
Does the Contractor bear the losses of 1% of additional tax from his each invoice when he claims Secured Advance or get benefit of 75% advance each month .
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?