Delay at the notification of client for start a part of
In the Open Standard
Emre BayrakMember for 23 years 5 months
- Created
- 6
- 6
0
Hi everyone
As per my contract my client has to give a notification to me for to start for a part of the project in a defined time period. This partial construction is in the critical path of project.
Client stated that they will give their approval with same delay. For my EOT claim of time and cost. Which is best strategy?
A- Giving an early varying and give the estimated cost effect of their delay as per a specific time period such as weeks or months.
B- Just give notification and record make claim after the costs are accrued.
What categories of cost I have to claim besides my time-related costs?
Regards
Emre
As per my contract my client has to give a notification to me for to start for a part of the project in a defined time period. This partial construction is in the critical path of project.
Client stated that they will give their approval with same delay. For my EOT claim of time and cost. Which is best strategy?
A- Giving an early varying and give the estimated cost effect of their delay as per a specific time period such as weeks or months.
B- Just give notification and record make claim after the costs are accrued.
What categories of cost I have to claim besides my time-related costs?
Regards
Emre
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?