FIDIC 1987 reprinted 1992 Clause 52.2
In the Open Standard
Anthony ScarlettMember for 21 years 2 months
- Created
- 7
- 3
0
Does anyone have any experience of the application of the second paragrpah of 52.2 in the 1987 Civil FIDIC?
The pargraph states:
"Provided also that no varied work instructed to be done by the Engineer pursuant to Clause 51 shall be valued under Sub-Clause 52.1 or under this Sub-Clause unless, within 14 days of the date of such instruction and, other than in the case of ommited work, before the commencement of the varied work, notice shall have been given either:
(a)by the Contractor to the Engineer of his intention to claim extra payment or a varied rate or price,or ..........."
My question is does this only apply to a rate change or does it apply to generally claiming ANY additional payment even if it is simply applying a contract rate to an additional quantity?
As you may have guessed, I have not notified under the Clause although I have notified under a different clause for some of the variations but not all.
Any thoughts?
Cheers,
Anthony
The pargraph states:
"Provided also that no varied work instructed to be done by the Engineer pursuant to Clause 51 shall be valued under Sub-Clause 52.1 or under this Sub-Clause unless, within 14 days of the date of such instruction and, other than in the case of ommited work, before the commencement of the varied work, notice shall have been given either:
(a)by the Contractor to the Engineer of his intention to claim extra payment or a varied rate or price,or ..........."
My question is does this only apply to a rate change or does it apply to generally claiming ANY additional payment even if it is simply applying a contract rate to an additional quantity?
As you may have guessed, I have not notified under the Clause although I have notified under a different clause for some of the variations but not all.
Any thoughts?
Cheers,
Anthony
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?