Variation of Work and As Impacted schedule
In the Open Standard
Puneet GuptaMember for 21 years 5 months
- Created
- 1
- 3
0
Hi
I have one doubt on Impacted schedule, let me start with an example.
I have a baseline schedule and to create an as impacted schedule i started putting delays on it because of law & order, variation of work & monsoon.
and each time i put a delay , i reschedule my prograame to see the impact , i also tried the same thing in excel using window analysis and also in Primavera, now the problem comes when few of my Vows are coming irregularly and not coming within the impacted duration, i mean say Early Finish of impacted activity is 10 day and Vows are coming on the 20th day, in between the 10 & 20 day there is no other delay,
what will be the best approach to repersent such scenario to compare my As-impacted and As-Built schedule.
I hope you all can guide me better.
Regards
I have one doubt on Impacted schedule, let me start with an example.
I have a baseline schedule and to create an as impacted schedule i started putting delays on it because of law & order, variation of work & monsoon.
and each time i put a delay , i reschedule my prograame to see the impact , i also tried the same thing in excel using window analysis and also in Primavera, now the problem comes when few of my Vows are coming irregularly and not coming within the impacted duration, i mean say Early Finish of impacted activity is 10 day and Vows are coming on the 20th day, in between the 10 & 20 day there is no other delay,
what will be the best approach to repersent such scenario to compare my As-impacted and As-Built schedule.
I hope you all can guide me better.
Regards
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?