Malmaison
In the Open Standard
David WaddleMember for 23 years 8 months
- Created
- 2
- 3
0
In the Malmaison case, Dyson J determined that if there were two concurrent causes of delays, one being a contractor culpable delay eg lack of resources, and the other being a relevant event, eg exceptional inclement weather; the contractor is entitled to an extension of time for the relevant event (assuming it is on the critical path).
Why is it that the contractors culpable delay is ignored? How is ’concurrent’ defined? Does it mean that both started on the same day or simply that one takes place during the life of the other?
Why is it that the contractors culpable delay is ignored? How is ’concurrent’ defined? Does it mean that both started on the same day or simply that one takes place during the life of the other?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?