Completion and Acceptance of the Work
In the Open Standard
Norzul IbrahimMember for 20 years 10 months
- Created
- 1
- 2
0
Hi,
Based on my experience in the oil refining industry, we normally have the following to differentiate the stages of completion of the project.
1) Mechanical Completion (MC)
2) Ready For Start-Up (RFSU)
3) Provisional Acceptance (PA)
4) Final Acceptance (FA)
The above will also normally tied to the payment milestones. What is your experience?
Thanks
norzul
Based on my experience in the oil refining industry, we normally have the following to differentiate the stages of completion of the project.
1) Mechanical Completion (MC)
2) Ready For Start-Up (RFSU)
3) Provisional Acceptance (PA)
4) Final Acceptance (FA)
The above will also normally tied to the payment milestones. What is your experience?
Thanks
norzul
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?