Give Suggestions to Claim
In the Open Standard
Karthik KumarMember for 20 years 5 months
- Created
- 11
- 1
0
Hello
This is an on going project in Miltary Hospitals.As per Contract there are 12 Zones Maintainence Works Like Replacing AHU and Installation of new FCU etc.And the Contract Period is nine months.
But Client gave Clearence only two Zones to work and small additional job that not in scope of Contract in the nine month contract period.
Now nine month contract time is finished and Clent is stared to give clearence other two new Zones for contractor.
In this Case My Contractors Manager Wants to Claim the amount from Client for his late Clearence for the remianing Zones in the above Project .
Plssssssss help
This is an on going project in Miltary Hospitals.As per Contract there are 12 Zones Maintainence Works Like Replacing AHU and Installation of new FCU etc.And the Contract Period is nine months.
But Client gave Clearence only two Zones to work and small additional job that not in scope of Contract in the nine month contract period.
Now nine month contract time is finished and Clent is stared to give clearence other two new Zones for contractor.
In this Case My Contractors Manager Wants to Claim the amount from Client for his late Clearence for the remianing Zones in the above Project .
Plssssssss help
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?