Activities not started against scheduled

Giji ThomasMember for 20 years 2 months
Created
3
2
0
Can anybody help me on this subject?

I have target & udate. From update, how I can filter the activities, which are not started against schedule.

3 replies

Oldest first
  1. 0
    Sunil Kumar ·
    Use Filter with Percent complete is equal to zero which will give you activities not started in your update.
  2. 0
    Steven Oliver ·
    Depends on the software you are using.
    P3 has a field "Variance Target 1 Early Start", not sure, but that may be useful.
  3. 0
    Giji Thomas ·
    Hi Steeven,

    This way it is correct, but some more

    If compaire VARIANCE TARGET-1 Es & EF with
    VARIANCE TARGET-1 LS & LF, showing all activities not started against schedule upto the data date.(Incl. float)

    Filter is like:

    Level-1

    VARIANCE TARGET-1 EARLY START - LT- 0

    Level-2

    Actual Dates -WR- Project Start date to data date (update)

    Level-3

    %age Complete -WR - 1-99