Liquidated Damages
In the Open Standard
Samagata ChakravortyMember for 20 years 10 months
- Created
- 9
- 4
0
Hi,
can any one comment on the following,
if the contractor delays completion but no effective non-completion certificate is issued by the architect/engineer under a JCT contract,will this mean that the employer loses the right to deduct liquidated damages?
regards
Sam
can any one comment on the following,
if the contractor delays completion but no effective non-completion certificate is issued by the architect/engineer under a JCT contract,will this mean that the employer loses the right to deduct liquidated damages?
regards
Sam
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?