both client and contrator delay
In the Open Standard
ME
Mohamed ElghayeshMember for 20 years 2 months
- Created
- 22
- 2
0
if it is plan to start activity (A) on 1/8/2006
the client isuue variation order on 25/7/2006 to start activity (B).
activity (B) needs 35 days to complete and activity (A) can not start without finishing activity (B).
so it is clear that it will be claimed for 30 days.
but if the contractor was not ready on 25/7/2006 to start activity (A)after 5 days also he was not ready even after 35 days.
is the contractor has a right to claim about the V.O because he suppose to make acceleration to over come his delay without the V.O Duration
22 replies
Oldest first- 0JAJawad Al-Nimri ·dear mohamad,
I do not understand, you mentioned that A can not start except after b, so the planned start for A is now 1/8/06 + 35 days.
you must update your schedule, if it is so then i believe there is no concurrency.
please clarify and detail your question a bit more,
Regards, - 0ZHZhang Haixiang ·if i’m not wrong. there’re two things caused delay of task A.
one is the VO, the other is something from the contractor.
If i’m the client, to be fair, i’ll give 30days to the contractor for task A,but the contractor should be responsible for any delay beyond 30days.
I believe there will be some clients that will refuse to give more time (or at least cut the payment,apply penalty...)when he find out that the contractor can not be on schedule even there’s no VO.
It’s a classic debate, no right answer. - 0AFAndrew Flowerdew ·John,
Given the amount of times the problem arises, you’d have thought it would have a settled solution by now!
In common law countries it is GENERALLY the case that if the contract says the contractor is entitled to an EoT for a certain event, and that event occurs AND causes delay to the completion date, then the contractor gets an EoT irrespective of any contractor delay occurring at the same time. (often called the "Malmaision" approach after the court case it comes from) - 0JWJohn Whitney ·Andrew,
Absolutely. Still, if it were settled, how would we keep the lawyers out of the pubs?
Interesting to see that many clients in the power plant field (especially those in the US) are now increasingly trying to nail down the concept of concurrent delay at the bidding stage - all in their favour, of course! I was confronted with one such odious clause in a recent bid, and immediately threw it back with the Malmaison position. Of course, the client’s lawyers countered with another case which said the complete opposite!
We finally resolved it after weeks of argument by calling it a draw and deleting their proposed clause - but only after I said I would rather take a chance in arbitration than have our people sign their draft as it stood.
Cheers,
John - 0JWJohn Whitney ·Uri,
Forgive my intrusion...but I think you are right on this. Indeed, the phrase "concurrent delay" is often a misnomer. While we often see the effects of delays being in parallel between client/contractor, almost always the causes of those delays emerge sequentially, one after the other. That being the case, they should be analyzed in chronological order under a time impact analysis.
I think we all have to very careful when we talk about "concurrent" delays. There is a lot of misinformation and confusion around concerning this subject, and I feel that the lack of a settled legal definition has a large part to play in this.
John - 0USUri Shachar ·John,
Your ’intrusion’ is most welcomed. I like your reference to delays being analysed in chronological order using TIA.
Unfortuantely, there is multiple terminilogy associated with concurrent delays such as "overlapping delays" (is it the same as concurrent delays?), overarching delays etc.
- 0AFAndrew Flowerdew ·Uri,
Yes, you are right in my opinion about cause but as John and yourself said - different people take the word to mean different things.
Concurrent, parallel, overlapping and many other terms are used, concurrent delay sometimes being distinguished from concurrent effect just to confuse the matter more.
I guess it’s abit like T.I.A - no recognised standard on how it should be done - maybe we should write one! - 0USUri Shachar ·Guys,
Please correct me if I’m wrong, I suspect some of the terminology I was not sure about refers to the "value" of delays i.e. even though delays can be concurrent one delay can be the prevailing or the predominant delay compared to the other delay(s).
In other words, my understanding is that even though, say, (the cause of) delay A occured prior to (the cause of) delay B, still delay B may be the prevailing delay and therefore any entitlement will be determined considering B and not A. - 0AFAndrew Flowerdew ·Uri,
That would depend on what legal system you are working with and the exact wording of the contract. All abit of a minefield, with various different legal arguments possible. As yet non of the approaches universally being accepted as the correct way to approach concurrent delay. There have been several previous threads on this subject which may be of help - or just serve to confuse!!!! - 0AFAndrew Flowerdew ·Oliver,
The SCL Protocol says TIA is the prefered method on analysis, but doesn’t tell you how to do it.
As for concurrent delay, the Protocol sets out one way of dealing with it - substantially along the lines of the law as it stands but with an American slant, but I know a few people (mostly lawyers!) who point out that you can only decide how concurrent delay should be dealt with when you know if the contract has anything to say about it. Can’t say that is wrong, some think the Malmaison approach is applicable to JCT contracts only, some (most) think it has a more universal application.
Most standard forms don’t say anything about concurrent delay and so the Protocol COULD be applicable, but these days alot of people are amending terms to try and deal with the problem. Some have sucess, others don’t - they end up putting time at large and creating bigger problems!
Personally I don’t think the confusion is a problem of law, it’s a problem of contract drafting.
Charleston - it would be good to write a TIA spec with the input from all the people on this site - I don’t think it could be done actually on the site so if anyone’s interested send me a personal message and we’ll see what can be done. - 0AAAshraf Alawady ·Coming back to the original question"if it is plan to start activity (A) on 1/8/2006 the client isuue variation order on 25/7/2006 to start activity (B). activity (B) needs 35 days to complete and activity (A) can not start without finishing activity (B). so it is clear that it will be claimed for 30 days. but if the contractor was not ready on 25/7/2006 to start activity (A)after 5 days also he was not ready even after 35 days. is the contractor has a right to claim about the V.O because he suppose to make acceleration to over come his delay without the V.O Duration "
In my opinion ,the cotractor is entitle to get 30 days EOT but with out any associated cost.
the reason is that ’by issuing the V.O to the contractor on 27/7/2006 to start activity B so this variation will prevent the contractor from completing activity A regadless the current situation in the project because we have to answer an immportant question(what will be the case if the contractor was refoomed well ,and his progress were in compliance with the programme and the date of completion,and this variation has issued at this stag.)
so definitly the contractor is entitled for EOT but due to the recorded delays from his side ,he will not be entitled
for the associated cost.
This is my own judgement.
GOOD LUCK - 0AFAndrew Flowerdew ·Uri,
The contractor may or may not be entitled to money - just depends on what your contract says. He will at least be entitled to the direct cost of doing the work and depending on how your contract works, may be entitled to EoT costs.
On the information you have stated, the contractor is entitled to 30 days EoT but you haven’t mentioned issues such as lead in times for operations, etc that need to be considered. - 0XPX Planner ·Dear Mohamed,
IMHO, i think u should be considering two things,
1- what was the actual situation at the time then, i mean u should look at the monthly update and u will be able to define if the contractor able or not, i believe if he was in delay already and ur V.O. will cause more delays (next update) then E.O.T can be garnted without any cost impact.
2- i think the acceleration and recovery are issues based on procedures so again if the contractor had the intention to setup a protocol to recover himself on the a/m period,then there should be correspondences on table to support your file.
Regards,
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?