Submittals and Transmittals

Omar KeilaniMember for 20 years 4 months
Created
3
2
0
Dear Guys, in Contract Documents , What is the difference between submittals and Transmittals ? which comes first ?
thank you

3 replies

Oldest first
  1. 0
    Andrew Flowerdew ·
    Omar,

    May be one and the same thing, may be different!!!!!!!!

    What they are really depends on what you use them for.

    Transmittal would normally be a record of anything you send to somone else, eg letters, etc

    Submittal would normally be a record of anything you submit to somone else for example, for approval - and may have a transmittal to go with it.
  2. 0
    Akhilesh Shukla, CCE EVP PMP ·
    Hi Friendz
    my submission to this is -

    Submittal is informations provided to other parties and it attracts some actions ( review, study, comment, confirm etc etc.) to be followed by the recipient.

    while, transmittal is merely for the information purpose and in normal circumstances does not abide by following actions.

    regards

    Akhilesh shukla
  3. 0
    Ashraf Alawady ·
    I agreed with anderw interpretation.