EOT CLAIM, DELAY CLAIM

Remon RemonoMember for 20 years
Created
15
2
0
HI ALL,
I HAVE TWO QUESTIONS.
1. I AM PREPARING EOT CLAIM, I NEED SOME HELP IN THIS REGARD. I MEAN YOU FELLOW PLANNERS HAVE ALREADY MADE CLAIM I CAN FOLLOW IN PREPARING MY CLAIM.

2. ANOTHER ISSUE, I FOLLOWING ANOTHER PROJECT IN WHICH THE CLIENT DELAY US IN ONE ITEM MORE THAN 150 DAYS BUT WE MANAGED TO HANDOVER THE PROJECT BEFORE I50 DAYS FROM THE CONTRACTUAL FINISH DATE. WHAT I CAN CLAIM FOR AND HOW TO CALCULATE THE DELAY COST.

PROJECT DURATION = 730 DAYS
ESTIMATED DELAY TIME BY CLIENT = 150 DAYS
PROJECT COMPLETION DATE NOV. 2006
ACTUAL COMPLETION DATE = JUNE 2006

DO I HAVE THE RIGHT TO CLAIM FOR IDLE EQUIPMENT & LABOURS, AND HOW TO ESTIMATE THE COST OF SUCH DELAY.

BEST REGARDS,

REMON REMONO








15 replies

Oldest first
  1. 0
    Ashraf Alawady ·
    1-For (150days) the estimated delays, did you got any approvals or acceptance from the client/engineer.

    2-Did you accelerated the works to finish the works on June 2006 instead of Nov.2006 and is there any official instruction to do so.

    we need your clarification,please.


  2. 0
    Andrew Flowerdew ·
    Remon,

    and to add to ashrafs’ request, what did you original programme show as a completion date?
  3. 0
    Anoon Iimos ·
    and please don’t shout, we’re professionals here!
  4. 0
    X Planner ·
    kindly, expand abit more

    what kind of client’s delays?

    what is the planned finish date of the program?

    what is the impact of this delay on the program?


  5. 0
    Remon Remono ·
    hi,
    type of delay: late approvals,late RFI reply, change of design.

    completion date as per program is Nov 2006

    thanks
  6. 0
    X Planner ·
    well, i believe u already issued N.O.Claims along the project durations and i’m not sure about the time frame represented by ur contract to submit the detailed claim which should contain at least:

    1- Time impact analysis representing the impact of these delays SEPARATLEY ONE A TIME.

    2- All supportive data just like letters, drawing registers and RFI’s register.

    3- i’m sure that contract must say something here regarding design changes thing (to be considered too)

    i know it is not an easy task, but i think if u considered the approvals in your program from the begining , things would be more easy for u.

    Good luck
  7. 0
    Ashraf Alawady ·
    Can you collect all those queries and rewrite the situation clearly in order to be able to provide you with our judgement and assessment.
  8. 0
    Ruben Quintal ·
    remon,

    if theres a written instruction from the client for you to accelerate the programme, then you have the rigth to claim for an acceleration cost, otherwise it is presumed that finishing the project ahead of time is your prerogative and the client has no obligation to any consequences that it brought.

    regards
  9. 0
    Shareef Abdul Azeez ·
    RUBEN

    I have the same say on this. You should have shown the impact of the delay caused by the client (this should have an impact finish date ie this delay should have delayed the project finish date) ; & thus you should have given a revised programme that you have to accelrate the works to pull back the project finsh date and could claim on the cost for acceleration.( unless your programme was a very loose programme giving a lot of float)

    Since it looks like you have done nothin in this regard your claim would be tough to go for.
  10. 0
    Shareef Abdul Azeez ·
    RUBEN

    I have the same say on this. You should have shown the impact of the delay caused by the client (this should have an impact finish date ie this delay should have delayed the project finish date) ; & thus you should have given a revised programme that you have to accelrate the works to pull back the project finsh date and could claim on the cost for acceleration.( unless your programme was a very loose programme giving a lot of float)

    Since it looks like you have done nothin in this regard your claim would be tough to go for.
  11. 0
    Andrew Flowerdew ·
    Remon,

    This thread seems to have lost its way slightly.

    Have a look back on the comments and put together the answers - we might be able to help you then.
  12. 0
    Ashraf Alawady ·
    Remon,
    Your clarification is required in the light of all our perviouse posts in order to continue this thread and reach to final conclusion.
  13. 0
    Stuart Ness ·
    Remon,

    At the risk of sounding superfluous, what does your Contract state about time limitation for submitting a claim (if any) and in regard to giving notice of a claim(if any)?

    Stuart

    www.rosmartin.com
  14. 0
    Pardeep Kumar ·

    Hi,I want to calim EOT due to

    Hi,

    I want to calim EOT due to variation of Drawing, and exra work.

    Kindly some one share me which clause will be use , please share me letters.

  15. 0
    Mike Testro ·

    Welcome to planning

    Welcome to planning planet

    Please set up a new topic - not add to an old one.

    It would help if you told us the form of contract you are using.

    Best regards

    Mike Testro

Log in or join to reply