EOT CLAIM, DELAY CLAIM
In the Open Standard
Remon RemonoMember for 20 years
- Created
- 15
- 2
0
HI ALL,
I HAVE TWO QUESTIONS.
1. I AM PREPARING EOT CLAIM, I NEED SOME HELP IN THIS REGARD. I MEAN YOU FELLOW PLANNERS HAVE ALREADY MADE CLAIM I CAN FOLLOW IN PREPARING MY CLAIM.
2. ANOTHER ISSUE, I FOLLOWING ANOTHER PROJECT IN WHICH THE CLIENT DELAY US IN ONE ITEM MORE THAN 150 DAYS BUT WE MANAGED TO HANDOVER THE PROJECT BEFORE I50 DAYS FROM THE CONTRACTUAL FINISH DATE. WHAT I CAN CLAIM FOR AND HOW TO CALCULATE THE DELAY COST.
PROJECT DURATION = 730 DAYS
ESTIMATED DELAY TIME BY CLIENT = 150 DAYS
PROJECT COMPLETION DATE NOV. 2006
ACTUAL COMPLETION DATE = JUNE 2006
DO I HAVE THE RIGHT TO CLAIM FOR IDLE EQUIPMENT & LABOURS, AND HOW TO ESTIMATE THE COST OF SUCH DELAY.
BEST REGARDS,
REMON REMONO
I HAVE TWO QUESTIONS.
1. I AM PREPARING EOT CLAIM, I NEED SOME HELP IN THIS REGARD. I MEAN YOU FELLOW PLANNERS HAVE ALREADY MADE CLAIM I CAN FOLLOW IN PREPARING MY CLAIM.
2. ANOTHER ISSUE, I FOLLOWING ANOTHER PROJECT IN WHICH THE CLIENT DELAY US IN ONE ITEM MORE THAN 150 DAYS BUT WE MANAGED TO HANDOVER THE PROJECT BEFORE I50 DAYS FROM THE CONTRACTUAL FINISH DATE. WHAT I CAN CLAIM FOR AND HOW TO CALCULATE THE DELAY COST.
PROJECT DURATION = 730 DAYS
ESTIMATED DELAY TIME BY CLIENT = 150 DAYS
PROJECT COMPLETION DATE NOV. 2006
ACTUAL COMPLETION DATE = JUNE 2006
DO I HAVE THE RIGHT TO CLAIM FOR IDLE EQUIPMENT & LABOURS, AND HOW TO ESTIMATE THE COST OF SUCH DELAY.
BEST REGARDS,
REMON REMONO
15 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?