Project Close Out Flow Chart or Check List

Mohamed SahirMember for 20 years
Created
2
1
0
What is Project Close Out Check List??

2 replies

Oldest first
  1. 0
    John Lawson ·
    Hi Mohamed

    Usually just a list of actions that need to be completed at the completion of a contract / project, mind some contract documents may have specificly identified requirements.

    The client may issue a list or more usual to be developed by Client / Contractor.

    The type of items could be, Issue Close out Report, Issue As Build Drawings, Issue As build Documentation, Issue of Handover Documentation, Material / Financial Reconciliation, Demobilisation of Site, Removal of Surplus Materails etc.

    Regards

    John
  2. 0
    Peter Holroyd ·
    Most Clients that have a formal project delivery process have specific deliverables required at the end of each stage or phase. The Close Out Check List is merely such a list of required documents to be produced by the project in the last project delivery stage. A flow chart would show any dependencies between the deliverables.

    For Close Out you would be looking for

    Tech Docs AFC / As-Built handed over
    Manuals in place
    Maintenance Systems Loaded
    Commercial Close Out
    H&S Files handed Over etc
    On-going support identified etc

    This usually all happens with a Project Close Out Report.