How to calculate suspension reimbursement?
In the Open Standard
Dana QandahMember for 20 years 2 months
- Created
- 3
- 4
0
The following costs are recoverable during a suspension period:
1. Demobilization and remobilization costs.
2. Idle manpower.
3. Idle equipment.
4. Depreciation on fixed assets
5. Site overheads.
6. Head office overheads.
Any other suggestions/ breakdown?
But will the number of staff remain the same? What if the contractor couldn’t minimize it ? Can the contractor reimburse their salaries as if they are working full hours?
Assume the suspension is from the owner.
What about equipment,? Depreciation or rental cost?
1. Demobilization and remobilization costs.
2. Idle manpower.
3. Idle equipment.
4. Depreciation on fixed assets
5. Site overheads.
6. Head office overheads.
Any other suggestions/ breakdown?
But will the number of staff remain the same? What if the contractor couldn’t minimize it ? Can the contractor reimburse their salaries as if they are working full hours?
Assume the suspension is from the owner.
What about equipment,? Depreciation or rental cost?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?