Hi Grace
Welcome to Planning Planet.
Firstly it is not a good idea to wake up long dead threads - you should start a new query.
As far as I recall the SIA was a variant of the old JCT forms and the remeasurement - pricing rules were similar.
If the re measured work is similar to that measured then the contract rates are applied.
If the re measured work is different in some respects - ie slab formwork at a different height - then the rate should be adjusted commensurately.
If the re measure is completely different then a new rate has to be applied.
If by PC rate you mean something completely different to a BOQ rate then tell us what you mean.
Best regards
Mike Testro