CONCURRENT-ENTITLEMENT FOR PROLONGATION COST
In the Open Standard
Prabu DevaMember for 19 years 8 months
- Created
- 1
- 3
0
THE CONTRACTOR IS DELAYED SAY 10 MONTHS TO THE PROJECT COMPLETION DATE, WHILE THE CONTRACTOR IS IN DELAY THE CLIENT ISSUES A VARIATION ,WHICH ALSO REQUIRES 10 MONTHS TO COMPLETE.( FORECAST PROJECT COMPLETION DUE TO CONTRACTORS DELAY AS WELL AS THE VARIATION IS SAME)
CAN THE CLIENT GIVE THE CONTRACTOR EOT WITHOUT PROLONGATION COSTS,SINCE THE CONTRACTOR IS DELAYED IN ANY CASE
CASE-2 CLIENT INSTRUCTION REQUIRES EXTENDING CONTRACT BY 15 MONTHS,CONTRACTOR IS DELAYED SAY 10 MONTHS,WHAT IS THE CONTRACTORS ENTITLEMENT
CASE-3 CLIENT INSTRUCTION CAUSES DELAY TO THE PROJECT BY 3 MONTHS,CONTRACTOR CONCURRENT DELAY IS 10 MONTHS,CAN THE CONTRACTOR ESCAPE FROM BEING PENALISED FOR THE CLIENTS CONCURRENT DELAY OF 3 MONTHS
CAN THE CLIENT GIVE THE CONTRACTOR EOT WITHOUT PROLONGATION COSTS,SINCE THE CONTRACTOR IS DELAYED IN ANY CASE
CASE-2 CLIENT INSTRUCTION REQUIRES EXTENDING CONTRACT BY 15 MONTHS,CONTRACTOR IS DELAYED SAY 10 MONTHS,WHAT IS THE CONTRACTORS ENTITLEMENT
CASE-3 CLIENT INSTRUCTION CAUSES DELAY TO THE PROJECT BY 3 MONTHS,CONTRACTOR CONCURRENT DELAY IS 10 MONTHS,CAN THE CONTRACTOR ESCAPE FROM BEING PENALISED FOR THE CLIENTS CONCURRENT DELAY OF 3 MONTHS
1 reply
Oldest firstLog in or join to reply