Error in pricing
In the Open Standard
Raphael Adeyemi, CCP, MNIQS, RQS, MQSiMember for 19 years 4 months
- Created
- 7
- 3
0
I am presently on a water project under FIDIC hybrid contract in which few fitting items were priced say BHD100,000.00 instead of BHD100.00. I guess thi was as a result of coma wrongly. The contract is in operation for over a yr. It was not discover at the tender evaluation process.
The question is The Consultant has issued instruction for the items not to be purchased and intend to varied the item. The Contractor is of the opinion that he is entitled to loss of expected profit as this amount to over 10% of the total contract.
My opinion is that the Consultant is trying to correct the mistake made at the tender evaluation and using Caluse 51.1 to varied the work. But I am in doubt if the Contractor is entitled to loss of expected profit. What do you think?
Awaiting response from u guys
The question is The Consultant has issued instruction for the items not to be purchased and intend to varied the item. The Contractor is of the opinion that he is entitled to loss of expected profit as this amount to over 10% of the total contract.
My opinion is that the Consultant is trying to correct the mistake made at the tender evaluation and using Caluse 51.1 to varied the work. But I am in doubt if the Contractor is entitled to loss of expected profit. What do you think?
Awaiting response from u guys
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?