Consultant Project Vehicle
In the Open Standard
Raphael Adeyemi, CCP, MNIQS, RQS, MQSiMember for 19 years 4 months
- Created
- 6
- 4
0
There is aproject where the contractor ommitted consultant project vehicle breakdown in preliminaries and general itesm though priced as included under Employer’sfacilities which includes, vehicle, mess staff, equipment,telephone /fax in the main BOQ. The consultant requested for the vehicle and subsequently deleted the amount inserted for this Employer facilities. Can the contractor recover the value for the project vehicle though not included in the P&G breakdown?.
Thanks
Thanks
6 replies