Schedule of application for subcontract

Skan BuMember for 20 years 4 months
Created
1
3
0
It is very common now in UK since the introduction of the HG&RA that main contractor issue a schedule of application.

This is just a list of dates which application from a s/c should be submitted so the application can be incorporated into the main contract valuation.

Sometimes this schedule of application also tie in with the payment schedule.

I have noticed some clever QSs or team have set it up in such a way that the MC kept their cash longer and so the S/C will not receive the monies certified by the PQS until much later eventhough thiss suppose to be a back to back contract. Although I noticed this but due to the lack of knowledge on the legal position, I am not sure whether it can be challenged.

Can anyone explain what is the legal position for the S/C in cases like this and whether anyone else have had any experience on this issue.

Thanks

1 reply

Oldest first
  1. 0
    Andrew Flowerdew ·
    Not quite sure what you are trying to explain so the only answer I can give is that if the provisions of the contract do not comply with the provisions of the HGCR Act with regard to payment, then the relevant provision of the Scheme for Construction Contracts replaces it.