Variations Order

Raphael Adeyemi, CCP, MNIQS, RQS, MQSiMember for 19 years 4 months
Created
3
3
0
I want to know if anyone had been in a situation an error in the BOQ rate is too low with substantial quantities and another item with high rate with few quantities.

The main question is a variation to the item that is priced too low with substantia quantities arose. Also there is a variation order of Omission to the item priced tooo high. What is the best approach for the Contractor to go about this.

Waiting to hear from you guys

3 replies

Oldest first
  1. 0
    Andrew Flowerdew ·
    Raphael,

    Starting position is that you’re stuck with them. You win some, you lose some, that’s the nature of business.

    Should a variation (rather than omission) come up you would have to try and argue that the conditions / characteristics that you are now performing the work under is sufficiently different from that you priced to justify a re-rate. That may only apply to the varied work though.
  2. 0
    Raphael Adeyemi, CCP, MNIQS, RQS, MQSi ·
    Thanks Andrew

    I guess that is the begining
  3. 0
    Bolisetti Jogiraju ·
    Raphael !

    Nothing more than what Andrew mentioned.

    Cheers