NEC Contract

Francis Moyalan, PMP,PMI-SPMember for 21 years 8 months
Created
1
2
0
Hi All,

Anyone having any knowledge about NEC-3 type of contracts,

This is presently used By a client in UAE for their upcoming massive development project,

All I know is, it is applicable for those projects in which client needs to share the risk with the vendors/contractors by making a jv with them,

Can anyone ponder more insight into this topic,

Cheers

Francis Varghese

1 reply

Oldest first
  1. 0
    Oliver Melling ·
    Francis,

    I don’t think this target price contract type is solely for the NEC3 suite of contracts.

    However, a target price contract is one where a ’target’ price is agreed in the planning stage of the project.

    The risk is shared between the contractor and the client by agreeing that any overpspend will be shared. I have come across a few different methods such as splitting the overspend by a percentage or making the overspend reimbursible at full rate minus profit.

    HTH

    Oliver