Methods of Analysis

Toby HuntMember for 19 years 2 months
Created
5
2
0
Dear All

This topic may have been covered extensively in the past, but on reading the recent Mirant -v- Over Arup judgement which mentioned "watershed" analysis, I wonder if there is common agreement on the methods of retrospective analysis available to be used.

As I understand it there are 4 different methods of analysis; As Planned -v- As Built, As Built but For, As Planned Impacted and Time Impact Analysis.

I would class windows (also known as timeslice) and watersheds as processes rather than methods of analysis. All methods of analysis can be carried out in windows and watersheds instead of taking the whole contract period as one.

Does anyone disagree with this classification of methods and processes?

Regards

Toby

5 replies

Oldest first
  1. 0
    Uri Shachar ·
    Toby,

    I believe that the four methods you’ve mentioned can be further classified to "forward looking" methods i.e. Prospective methods: As Planned Impacted and Time Impact Analysis and "backward looking" methods or retrospective: As Planned -v- As Built and As Built but For.

    However, I’m afraid some people get confused and call the Prospective methods Retrospective.

    is this only me or do we have an inconsistent terminology issue here?
  2. 0
    Toby Hunt ·
    Uri

    You may be right. For clarification, by retrospective I was meaning methods that could be employed after project completion rather than on a live project.

    I have seen a number of reports and had conversations with a number of self confessed delay analysts who have spoken of performing a "windows analysis" to ascertain cause and effect. When probed a little deeper, what it actually transpires they have done is an AP-v-AB analysis in windows.

    Also, the Judge’s ruling on Mirant will no doubt see a lot more claims of windows analysis as a methodology.

    Perhaps this sort of complication is why some people see delay analysis as a "black art"!

    Regards

    Toby
  3. 0
    Andrew Flowerdew ·
    Toby,

    Have said it many times on here - it would be nice to have a universally accepted definition of all the methods and guidance/standards as how each is to be performed.

    Unlikely to happen though.
  4. 0
    Toby Hunt ·
    Andrew

    I think you may be right!

    At least as a start the Great Delay Analysis Debate conducted by the SCL (see http://www.scl.org.uk/papers/papersummaries.php?PID=130&RID=439) discussed the 4 methodologies in some detail. However, the lack of clarity about process surrounding the use of these methods is still there.

    It doesn’t really help when judgements and pleadings refer to a delay analysis being carried out using (for example) "windows analysis" rather than "xxxx analysis in windows"

    Hey ho, onwards and upwards
  5. 0
    Charleston-Joseph Orbe ·
    Hello to All,

    The said case Mirant vs Arup open a new dimension on the way we take a serious look in establishing standard in project planning activities.

    A new term called "Window Anaylsis" against Watersheed Analysis

    ’windows’ analysis, where a series of snapshots of progress and potential causes of delay on the project at periodic points in the programme is analysed. Windows analysis is usually undertaken on a monthly basis.

    ’watershed’ analysis, where the snapshots are taken at critical milestones instead of regular periodic points.

    This is really great. I thank Clive, I think he was the one who give hints about this topic Mirant vs Arup.

    Please take note that window analysis is superior compared to watersheeds anaylsis

    I think window analysis is similar to monthy progress update but this is more on Analysing DELAYs to Critical Path.

    Cheers,