Time Impact Analysis (Prog Override vs. Retained Logic)

Hesham MahmoudMember for 21 years
Created
5
3
0

Is it the Contractor’s choice to adjust P3 scheduling settings to either progress override or retained logic while developing the impacted program? With the same logic, is the Contractor free to use the program "impact" technique, i.e. as planned, as built, or slice time?

Lets assume that none of the above issues are defined in Contract or agreed on through the use of SCL protocol for example!

Regards,



5 replies

Oldest first
  1. 0
    Ashraf Alawady ·
    Hi,Hesham
    progress override logic should be used for the horizontal projects like roads and infrastructures.
    retained logic should be used for the vertical projects like Buildings.

    THANKS
  2. 0
    Andrew Flowerdew ·
    Neither give the final answer, use whichever but be prepared to adjust the results if needed to reflect the reality of what happened when updating.
  3. 0
    Charleston-Joseph Orbe ·
    HI,

    Very interesting. I think depends on which side are you

    The bright side, if your are in the contractor side

    use retained logic to scare the project team in acting to mitigate delays, the top executive of the contractor are ignoramos always under the influence of commercial or contract department believing that claims for extension of time and associated cost will give them more profit than running the project as per baseline program or revised baseline program

    use progress overide if the project teams are enligthen, the contract department influence in site activities are minimal to the point of zero, progress overide will also make way to upgrade the program into live and realistic schedule activities.

    IF you are on the dark side, meaning, consultant, project manager, client. Always use retained logic to scare the contractor in doing there very best to achieve project goals.

    Cheers,

    Sensei
  4. 0
    Charleston-Joseph Orbe ·
    Actually,

    My post will not help anyone in the project team. But it is real experience.

    So go back to Post No. 3 by Andrew.

    But the best advice is just blend with the project team, like a TIMANO of the Bourne Identity series.

    I think this is one reason Primavera give this options. It will make us flexible and not dogmatic in our planning activities.

    Remember, planning is only a tools. There are lots of controversy and issues on the way planning are implemented in particular project.

    Cheers,

    Sensei


  5. 0
    Waleed Mahfouz ·
    WONDERFUL QUESTION, I THINK THE CONTRACTOR CAN’T ADJUST THIS OPTION WHEN UPDATING, BECAUSE IT WILL BE MISLEADING ACTION AND CAN’T MONITOR THE SITE WORKS.