Adjudication: a guide
In the Open Standard
Skan BuMember for 20 years 4 months
- Created
- 5
- 4
0
Hi,
Adjudication in UK say JCT form of contract.
What are the steps or relevant points:
Say a sub contractor (say groundwork&conrete)had not been pay for some works carried out for a Main Contractor on a project. The S/C obviously think the works are extra and was carried out say in December 06 and now in June 07, the MC still do not wish to pay.
What are the steps towards a possible adjudication?
Assume I am the site QS for the S/C and need to brief my Director, initially in bullet points & expand later & what he should consider first without going to a consultant.
Adjudication in UK say JCT form of contract.
What are the steps or relevant points:
Say a sub contractor (say groundwork&conrete)had not been pay for some works carried out for a Main Contractor on a project. The S/C obviously think the works are extra and was carried out say in December 06 and now in June 07, the MC still do not wish to pay.
What are the steps towards a possible adjudication?
Assume I am the site QS for the S/C and need to brief my Director, initially in bullet points & expand later & what he should consider first without going to a consultant.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?