FIDIC Clause
In the Open Standard
JD
Jineesh DathMember for 19 years 1 month
- Created
- 8
- 3
0
8 replies
Oldest first- 0SNStuart Ness ·OK - so some fell on stony ground!! ;-)
As you are aware, (Sub)Clause 8.3 of FIDIC (Red, Yellow and Silver Books) refers to the obligation for the Contractor to submit a Programme and also to the nature and extent of said Programme.
Clause 14 of Do. do. refers to Contract Price and Payment.
Where is the inconsistency between these two references?? - 0ADA D ·Absolutely true, but theres small difference in both forms:
CLAUSE 8.3 (1999)
The full role of the programme in the FIDIC form is not clear. One role of the programme in the FIDIC conditions is to allow the progress of the Works to be monitored. Although not expressly stated, it is suggested that in order to fulfill the functions required to monitor progress and predict future delays under the Red and Yellow Forms, the minimum requirement is a Prediction Programme in the form of a Linked Bar Chart. It is suggested that the Silver Form only requires a Bar Chart type of programme.
The programme is not used as a Compensation Programme, although it will be evidence of actual progress and of the reasonable time for issue of information. It is suggested that it would not be a "fair determination" to ignore the results of an analysis of extension of time based upon or using the Clause 8.3 programme. The programme defines, if not creates, time obligations, although not a contract document.
It is suggested that Employers should consider specifying a Network Analysis Programme and the form required as well as the software to be adopted, since this will allow easier reporting and monitoring of progress as well as analysis of compensation, particularly as each programme is required to be resourced.
CLAUSE 14 (1992 edition)
This version does not give the programme a significant place in the administration and management of the contract. The Contractor’s report on his method of working is distinct from the submission of a programme and there appears to be no requirement to link the two. The Contractor’s obligation to progress the Works is not directly related to the programme. The determination of any extension of time is based on actual delay and not analysis of the programme.
It is suggested that in order to fulfill the functions required under the ICE 7th Edition (1992) a Progress Programme in the form of a Bar Chart is all that is required. - 0SNStuart Ness ·
Not entirely sure why one needs to compare Clause 14 (1992) with Clause 8.3 (1999), other than to demonstrate that the former version made little reference to a project management facility that now lies at the heart of modern construction projects. No one in their right mind would consider not using some form of programme for any construction project, even a house extension!
Certainly the failure to emphasise the importance of a programme was a serious omission from the 1992 version, and this has been addressed - at least in part - by its subsequent inclusion.
As we know, the programme is there to make everyone’s life easier in managing complex (or even straightforward) projects. I am unconvinced, however, that formalising planning procedures into the Contract document is advantageous, since these need to be flexible to suit changing circumstances, and I do not think a ’one size fits all’ phylosophy is wise in this case. - 0RCRolando Caminero ·A well prepared plan defines the obligations not only by the Contractor but as well as those of others involved, Client, Material/Equipment Contractors, A/E Design group,including constraints due to site related reasons,
It transmit the mindset of the builder in diagram/chart form, who also needs contribution from other parties.
It must be flexible and rigid in a way,
Flexible to cope with actual conditions,
Rigid so as not to mislead other parties commitment,
If a planning programme is not a part of contract document?
why prepare one when there is no need to follow it?
go to a construction site and see if it is logical to work without a programme,