Contract Programme revision upon award of EOT.

Cherie S BlareMember for 20 years 9 months
Created
2
2
0
Dear all

What is the next step to the contract programme revision process when you are awarded an EOT from the client ?

Regards

CSB

2 replies

Oldest first
  1. 0
    Christian Adrian De Vera ·
    I suppose you need to revise your tracking & control data as well...
  2. 0
    Oliver Melling ·
    Create an EOT impacted contract programme for use as the newly agreed baseline.