No Subject Specified

Khawaja UddinMember for 20 years 8 months
Created
3
2
0
There are four different techniques to do the delay analysis
1-As-Planned Vs As-Built
2-Impacted As-Planned
3-Collapsed As-Built
4-Time Impact Analysis

My question are as follows,

Are these technique used under different circumstances?

or any of the technique can be used ,as we wish ?

WEhich one is most preferrable and acceptable technique widely used?
I will appreciate the answers
Thanks n Rgds

3 replies

Oldest first
  1. 0
    Oliver Melling ·
    khawaja uddin,

    Try reading this, you might find it useful.

    AACE International Recommended Practice No. 29R-03
    FORENSIC SCHEDULE ANALYSIS
  2. 0
    Oliver Melling ·
    Page 101 shows when it is best to use each method.
  3. 0
    Mike Testro ·
    Hi All

    The original post was:

    There are four different techniques to do the delay analysis

    1-As-Planned Vs As-Built
    Best used when Sub-Contract work is compressed between other trades.
    2-Impacted As-Planned
    Used for on-going work
    3-Collapsed As-Built
    Completely unreliable - don’t even go there.
    4-Time Impact Analysis
    Best for forensic analysis but must have accurate As Buit data to be effective.

    I hope this is clear

    Best regards

    Mike Testro

Log in or join to reply