Variation intiate from Contractor?
In the Open Standard
Gayantha AbeywardenaMember for 18 years 7 months
- Created
- 14
- 4
0
Dear All,
Here is one example i want 2 draw ur attention:
Contractor has to do Concrete with GI mesh Instead of GI mesh he is suggesting fibre reinforced (Fiber mix) concrete to avoid the GI mesh.
Contractor gains time advantage as proposed method is faster. and the required strenghth is achievable.
consultant give the approval subjected to cost saving
but in the actual cost is 5% more than the GI reinforced concrete.
What is the Contractors entitlement????
Here is one example i want 2 draw ur attention:
Contractor has to do Concrete with GI mesh Instead of GI mesh he is suggesting fibre reinforced (Fiber mix) concrete to avoid the GI mesh.
Contractor gains time advantage as proposed method is faster. and the required strenghth is achievable.
consultant give the approval subjected to cost saving
but in the actual cost is 5% more than the GI reinforced concrete.
What is the Contractors entitlement????
14 replies
Oldest firstLog in or join to reply