Skip to content

ENGINEERING CLAIM

Jorge FierroMember for 22 years 11 months
Created
4
3
0
Hi,

I am trying to justify overspending on Man Hours in Engineering because of the big, big... increasing in quantities.

Some of the increased quantities are demosntarble by changes but others not.

The problem is that is difficult to explain that I spend more resourses when i need to design bigger structures, pipes, etc.. inside the same phisical space. Design Disrruption.....

Any Idea??

4 replies

Oldest first
  1. 0
    Omer Hassan ·
    Can u please elaborate your question?

    Regards,
    Omer
  2. 0
    Jorge Fierro ·
    Thanks Omer,

    The question should be:

    Is it possible to structure a claim for increased quiantity of engineering (more piping, concrete, cables, etc...), without changes in the scope of work ?

    If yes, please an example.

    Thanks,

    Jorge
  3. 0
    Khawaja Uddin ·
    Hi,
    you can prepare your claim as a DAY WORK ,which includes the work you have done on certain dates and the eng. hr spent perform the work .
    Hope it may help you .
    Rgds
  4. 0
    Mike Testro ·
    Hi Jorge

    You do not say if you are trying to claim for extra time or money.

    As always it all depends on what it says in the contract.

    Usually extra work is recoverable in both time and money unless the Contractor has agreed to take on the risk.

    Best regards

    Mike T.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?