Time Limit For Time Plan Approval
In the Open Standard
Hemanth KumarMember for 23 years 11 months
- Created
- 11
- 4
0
Hi Gents
Client Gave us Access Dates To Their Premises For Work
6 Months Ago , in a meeting . Not With An Official Letter Or Mail.
A Time plan was submitted to client based on that immediately
There Was No Positive Reply To Reminders To Review & Approve .for almost 6 months
Now they are saying one of the access date we have shown in our plan is wrong (Which is True)
We arrived at a completion based on that (wrong ) access date
Questions :
1,Can a submitted plan can be taken as approved if no reply is given within a certain period ( Nothing mentioned in the contract )
2.Can we take the access date in our plan and proceed
with the delay calculation , ( There is Acces Delay Compared To Submitted Plan , But Not With Respected To The Given Plan By Client in an informal meeting )
Please Advice
Client Gave us Access Dates To Their Premises For Work
6 Months Ago , in a meeting . Not With An Official Letter Or Mail.
A Time plan was submitted to client based on that immediately
There Was No Positive Reply To Reminders To Review & Approve .for almost 6 months
Now they are saying one of the access date we have shown in our plan is wrong (Which is True)
We arrived at a completion based on that (wrong ) access date
Questions :
1,Can a submitted plan can be taken as approved if no reply is given within a certain period ( Nothing mentioned in the contract )
2.Can we take the access date in our plan and proceed
with the delay calculation , ( There is Acces Delay Compared To Submitted Plan , But Not With Respected To The Given Plan By Client in an informal meeting )
Please Advice
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?