important question in fidic?

Amro AhmedMember for 17 years 9 months
Created
7
3
0
Dear colleague,
I woulkd like to ask about information in fidic, my question is, do the client have the right to put program and do monitoring through it furthermore, don,t accept any dates not matching with it although contractor program is exist and approved and have the right to give instructions directly to contractor?

Thanks
Amro
eng_amrelsaied@hotmail.com

7 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Amro,

    The FIDIC is not specific on this actions by the client.

    But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.

    Basically, the client will only provide milestone dates, basic activities at level 1 or 2.
  2. 0
    Charleston-Joseph Orbe ·
    Amro,

    The FIDIC is not specific on this actions by the client.

    But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.

    Basically, the client will only provide milestone dates, basic activities at level 1 or 2.

    Cheers
    Happy Planning and Scheduling

  3. 0
    Charleston-Joseph Orbe ·
    Amro,

    The FIDIC is not specific on this actions by the client.

    But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.

    Basically, the client will only provide milestone dates, basic activities at level 1 or 2.

    Cheers
    Happy Planning and Scheduling

  4. 0
    Charleston-Joseph Orbe ·
    Amro,

    The FIDIC is not specific on this actions by the client.

    But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.

    Basically, the client will only provide milestone dates, basic activities at level 1 or 2. The

    Cheers
    Happy Planning and Scheduling

  5. 0
    Samer Zawaydeh ·
    Dear Amro,

    Per FIDIC 1999 clause 8.3, the Contractor shall submit a detail time program to the Engineer within 28 days from receiving commencement order.

    The Engineer reviews the submitted program and either approve it or send it back with comments for resubmittal.

    On larger projects, the Client might have a Construction Manager who is managing many Contractors. In this event, a separate Planning entity would be available at site to manage the entire works.

    The Contract requirements pertaining to the scope, milestones, and others must be listed in the program.

    If you have more specific questions, please let us know.

    Samer
  6. 0
    Amro Ahmed ·
    Dear Samer,
    Thank you for deatailed reply and for your great information but do the client have the right to apply his whole program and not accept any date for example for material submission not matching with his program furthermoe,you have soft copy for fidic specially about claims if you have could you provide me

    Thank you very much
    Amro
    eng_amrelsaied@hotmail.com
  7. 0
    Samer Zawaydeh ·
    Dear Amro,

    If the Contract has Milestone dates specified in it then it is binding to the Contractor to achieve and include in his submitted program of works.

    If the Contract is silent, then the only restriction is the end delivery date.

    If the Client has sufficient reason to reject any part in the submitted program of works "Material submittals" or others, then it is the Contractor’s responsbility to submit the necessary resources in written supporting his reasons for submitting the proposed program of works.

    Unless you have specific clause in your Contract stating that you must respects the dates the Client gives you for any part of the project, then your responsibility is to complete the job on time. The Program that you submit must show that, by showing all the necessary activities, milestones, resources, and durations to complete the project.

    A copy of the FIDIC hard or soft can be purchased from FIDIC at www.fidic.org for small fees.

    Good luck,

    Samer

Log in or join to reply