Force Majeure
In the Open Standard
Hemanth KumarMember for 23 years 11 months
- Created
- 13
- 4
0
A Marble Block Was Inspected Jointly By The Contractor & Consultantt In Intaly
When It Was Brought To UAE for a Hotel Project for Processing (ie Cutting And Ploshing) a majour fissure was found which made the whole block useless.
it took another 4 week for another block sourcing,approval , shipment etc
we lost 4 weeks
can this time can be claimed under force majeure??
Informal response from client was NO!
any similer claim experiances ?
When It Was Brought To UAE for a Hotel Project for Processing (ie Cutting And Ploshing) a majour fissure was found which made the whole block useless.
it took another 4 week for another block sourcing,approval , shipment etc
we lost 4 weeks
can this time can be claimed under force majeure??
Informal response from client was NO!
any similer claim experiances ?
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?