Lump Sum Contract.
In the Open Standard
Toh MichaelMember for 17 years 7 months
- Created
- 7
- 1
0
Dear All hope can have some further elaboration in this ..
1) how many type of lump sum contract we have ?
Currently we have a contract previously being sign as Lump Sum contract with a detail BOQ breakdown with quantities and unit rate for a ID construction project.
Current stage project finish 100% and the consultant QS is start to measure everything inside the BQ as compare to the as built at site.
What will be the stand : -
1) stop all the remeasurment of the contract carried out by the consultant QS ?
2) Limit the consultant QS only remeasure those item fall under VO only.
Kindly advised..
Cheers
Toh
1) how many type of lump sum contract we have ?
Currently we have a contract previously being sign as Lump Sum contract with a detail BOQ breakdown with quantities and unit rate for a ID construction project.
Current stage project finish 100% and the consultant QS is start to measure everything inside the BQ as compare to the as built at site.
What will be the stand : -
1) stop all the remeasurment of the contract carried out by the consultant QS ?
2) Limit the consultant QS only remeasure those item fall under VO only.
Kindly advised..
Cheers
Toh
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?