Dear All,

can any one explain me whats the necessity to include the "Defects Liabilty for the Demolition Package."

4 replies

Oldest first
  1. 0
    Nestor Principe ·
    Claims by others due to illegal disposal, damages to adjacent structures, uncompleted removal of substructures, etc.

    Cheers,
  2. 0
    Samer Zawaydeh ·
    Hi,

    Usually the general conditions of contract are custom tailered per the Contract needs. You need to object to it and get it cancelled, if you are certain that it does not make sense.

    Best Regards,

    Samer
  3. 0
    Zubair Taha ·
    Hi,
    got the point, thanks all of you for supporting.
  4. 0
    R. Catalan ·
    Zubair,

    To protect Client’s interests:
    - Cost of additional plant due to poor workmanship (non-compliance of obligations)

    - Cost to cover extension of performace guarantee if part(s) of the works cannot be used for its inteded purpose

    - Remedial works to adjacent properties

    Best regards,
    R. Catalan