Subcontractor claims-Cable pulling
In the Open Standard
Balu KarunakaranMember for 18 years 10 months
- Created
- 10
- 3
0
My company is into subcontracting of cable pulling for a big project.Iam facing some real stumbling blocks for EOT as given.
1.The prerequisites for cable pulling were delayed,which are not fully documented .What are the chances of getting an EOT.
2.The OD in baseline is much less than the actual onsite conditions.i.e when the OD for a cable pulling activity is 1,when the actual onsite duration is months
3.We didnt have much sophistication on the site and there was lack of supervision which made the project delayed and we exceeded our contractual duration.Is there any chances when we submit our EOT they can impose liquidated damages?
4.We dont have any preliminaries included in the BOQ,how can this be claimed?What % of the contractual value is usually EOT value?
Anticipating support from the members
Regards
Balu
1.The prerequisites for cable pulling were delayed,which are not fully documented .What are the chances of getting an EOT.
2.The OD in baseline is much less than the actual onsite conditions.i.e when the OD for a cable pulling activity is 1,when the actual onsite duration is months
3.We didnt have much sophistication on the site and there was lack of supervision which made the project delayed and we exceeded our contractual duration.Is there any chances when we submit our EOT they can impose liquidated damages?
4.We dont have any preliminaries included in the BOQ,how can this be claimed?What % of the contractual value is usually EOT value?
Anticipating support from the members
Regards
Balu
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?