Skip to content

Excessive Revised Construction Drawings

Raphael Adeyemi, CCP, MNIQS, RQS, MQSiMember for 19 years 4 months
Created
3
5
0
I was involved in a contract of luxirious private development that was contracted on FIDIC 87 Edition which is meant for contract with substantia design before final contract formulation.

In the course of the project, there were several designs or drawing review, there was a particulatr that was reviewed 34times for a contract that supposed to finish within 9months.

Secondly, there was a huge provisional sums included in the contract which the Client Project manager erroneously treated as Prime Cost items...., the works related were issued through Engineers Instructions as Nominated Subcontract. The resulted to significant delay

Thirdly,in the course of project progression, there were other Consultants on board not mentioned in the Tender and Contract documents. This resulted in communication gap in getting necessary approvals and drawings review.

Fourthly, the PM was performing the roles of an Engineer, by all means according to FIDIC, he is not

The Project was substantia delay and EOT was submitted which the PM recieved and declined action for over 3months.

Could you guys advise me what to do

Cheers

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Raphael,

    What is it that you are trying to accomplish and the other party is refusing your proposal.

    If you are talking about an EOT then you need to have the proper notification as per FIDIC. The Engineer has to reply within 42 days and not 3 months.

    Once you identify the problem, then we can assist you in solving it within the FIDIC clauses and conditions.

    With kind regards,

    Samer
  2. 0
    Roland Tannous ·
    Dear all,

    I do see the main problem right here. Been there done that. I think the main problem is the PM/engineer not cooperating. If you feel he is not respecting the contractual agreement I advise you get to arbitration (if there is a related clause) and certainly seek help from a well qualified construction lawyer.
    Good Day
    Roland Tannous
  3. 0
    Mike Testro ·
    Hi Raphael

    Your opening sentence starts "I was involved ..."

    Are you no longer part of this project?

    If not then any advice will be purely acedemic.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?