BIM Forensic Delay Analysis with 3d impacted models
In the Open Standard
Matthew EdwardsMember for 16 years 8 months
- Created
- 10
- 3
0
Hi all
We have started to get involved with BIM Frorensic delay analysis techniques using Asta Powerproject and Synchro. By taking an impacted contractors programme and comparing it against a model in 3d within synchro, this has led to a very accurate and graphically pleasing delay analysis technique.
I have been discussing this with some contacts about taking it a step further, and printing out each impact comparison of planned v actual timeframe to the model on a 3d printer.
Has anyone else tried this ?
What are your thoughts and would this be appealing to the judge ?
Regards
Matthew Edwards - www.ppm5d.ie
We have started to get involved with BIM Frorensic delay analysis techniques using Asta Powerproject and Synchro. By taking an impacted contractors programme and comparing it against a model in 3d within synchro, this has led to a very accurate and graphically pleasing delay analysis technique.
I have been discussing this with some contacts about taking it a step further, and printing out each impact comparison of planned v actual timeframe to the model on a 3d printer.
Has anyone else tried this ?
What are your thoughts and would this be appealing to the judge ?
Regards
Matthew Edwards - www.ppm5d.ie
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?