Delay Event -Payment?
In the Open Standard
Shah. HBMember for 17 years 10 months
- Created
- 5
- 1
0
Hi
In Time impact method ,for example Nov 2009 on wards payment was not paid by the client to the general contractor .The programme used to demonstrate the dealy is consented programme of works with cost loaded .
In that case updating the programme up to November and then introducing delay event as payment [ From Nov to JAN 2010] and activities whcih has not started due to delay in payment are tied with the delay event.
Is this way of presenting the delay will be acceptable by consultant ?
In Time impact method ,for example Nov 2009 on wards payment was not paid by the client to the general contractor .The programme used to demonstrate the dealy is consented programme of works with cost loaded .
In that case updating the programme up to November and then introducing delay event as payment [ From Nov to JAN 2010] and activities whcih has not started due to delay in payment are tied with the delay event.
Is this way of presenting the delay will be acceptable by consultant ?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?