Extraction licence -foreseeable requirement?
In the Open Standard
Gary WhiteheadMember for 17 years 6 months
- Created
- 4
- 4
0
The need to obtain an extraction licence for a small wind pump seems to have been overlooked until quite late in the day on one of my projects.
The contractor is saying this licence is for the service condition of the pump, and therefore not in their scope.
I’m leaning towards the argument that getting the necessary permits is their responsibility and even though not specifically mentioned in the contract, should have been reasonably foreseable by a competent contractor.
UK project, IchemE Target cost contract.
What’s your opinion?
The contractor is saying this licence is for the service condition of the pump, and therefore not in their scope.
I’m leaning towards the argument that getting the necessary permits is their responsibility and even though not specifically mentioned in the contract, should have been reasonably foreseable by a competent contractor.
UK project, IchemE Target cost contract.
What’s your opinion?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?