NEC3 with Target Cost.
In the Open Standard
Muhammad AnwarMember for 19 years 8 months
- Created
- 4
- 3
0
Gents,
We as contractor are working on NEC3 with target cost project. Please shed some light on the following cotractual issue.
We got delay to completion because of client. Work on the critical path was obstructed and we decided to work on non critical activity.
Client is using the augument, Obstrution on one activity does no stop you to jump on the next critical item. Although it was possible to work on the next item but was relatively less productive. He is using this argument that we are duty bound to mitigate the delay. which we have not put effort to do that.
Is he right in this argument and is there any court argument to develop better understanding on critical path management.
regards
Muhammad
We as contractor are working on NEC3 with target cost project. Please shed some light on the following cotractual issue.
We got delay to completion because of client. Work on the critical path was obstructed and we decided to work on non critical activity.
Client is using the augument, Obstrution on one activity does no stop you to jump on the next critical item. Although it was possible to work on the next item but was relatively less productive. He is using this argument that we are duty bound to mitigate the delay. which we have not put effort to do that.
Is he right in this argument and is there any court argument to develop better understanding on critical path management.
regards
Muhammad
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?